An Old Line Gets a Major Upgrade

Wood poles carry a 115-kilovolt line past homes and orchards on the older stretch between Big Eddy and Columbia Heights. A planned rebuild will install steel poles that are stronger, longer-lasting, and more resistant to wildfire.

A BPA-funded rebuild will improve reliability and wildfire resistance and make room for growth.

By Karen Heim

You’ve likely noticed the power lines that crisscross The Dalles, but you may never have thought about how old they are or how well they will hold up over time. Thinking about that is a big part of our job, and it’s why we plan ahead for the day a line needs to be replaced.

1 of those lines is a 115-kilovolt transmission line that has carried power 8.5 miles through The Dalles for decades, from Big Eddy Substation to The Dalles Substation. Transmission lines like this one move large amounts of high-voltage power between substations before it reaches the lines on your street. The oldest stretch of this transmission line is due for a major upgrade.

Northern Wasco County PUD is leading the rebuild, and the PUD’s transmission provider, Bonneville Power Administration, is paying for it. Your lights will stay on, with no power outages planned during this line replacement.

Where the Work Will Happen

From Big Eddy, the line passes through our Seufer, Columbia Heights, West 2nd Street, and W. 10th Street substations on its way to The Dalles Substation, where power continues to Hood River County.

The stretch between Columbia Heights Substation and W. 10th Street Substation was rebuilt about 20 years ago. While all the conductors will be replaced, most of the major construction will occur on the much older stretch from Big Eddy to Columbia Heights, which the PUD inherited from Pacific Power and Light. Where possible, crews plan to set the new poles in the same spots as the old ones.

What It Means for You

  • No planned outages. Your power stays on throughout the project.
  • Minimal street closures. When a short closure is needed, flaggers will be on site to direct traffic.
  • Possible easement outreach. An easement gives NWCPUD permission to access equipment on or near private property. If a pole being replaced is on or near your property, we may contact you about a new or updated easement.
  • No meaningful change in electromagnetic fields. EMF surrounds anything that carries electricity, from power lines to the wiring and appliances in your home.
The transmission line rebuild will ensure reliability for decades.

Some customer-owners have asked if this project will change EMF levels near the line.

“The line will run at the same voltage, along the same route, so the change in EMF from this project is so small, we likely couldn’t even measure it,” Chief Operating Officer Jeff Teel says. “If anyone has questions, we’re happy to talk them through.”

Why Rebuild It?

Summer heat is a challenge for the older stretch of line. Power lines can safely carry less electricity when it’s hot outside, and hot summer afternoons are when people in The Dalles need the most power to keep cool.

The new line will use an advanced high-temperature, low-sag conductor, a type of wire built to carry more power in the heat without drooping the way traditional wire does. It’s lighter than traditional wire with the same capacity, so we’ll be able to increase the capacity of the line without increasing the stress on our poles. Once the rebuild is finished, the line will be able to carry more power all year.

Along with the new wire, the rebuild will replace the old wood poles with steel poles. Steel holds up much better against wildfire, which matters for a line that runs through an area with elevated fire risk.

The new poles will also be strong enough to carry distribution lines—those that serve homes and businesses— underneath the transmission line. This underbuild will let us serve future growth on the east side of town.

“When we plan a project like this, we’re thinking about reliability decades out,” Jeff says. “More capacity gives us headroom on the hottest days, and steel poles reduce our exposure to wildfire. The underbuild sets us up to serve new load as our community grows.”

Why BPA Is Paying for It

BPA relies on this 115-kV line to carry power on to Hood River County, so the entire route must be strong. BPA identified the rebuild as a need and selected it as 1 of 13 projects in its Grid Expansion and Reinforcement Portfolio, a group of projects meant to support growth and reliability across the region.

“The grid doesn’t stop at the county line,” NWCPUD General Manager and CEO Roger Kline says. “Power headed to Hood River County travels through our system first, so when BPA invests in that path, the benefits land here, too. We get more capacity and a stronger line to serve The Dalles as we grow.”

What’s Next

The project is still in the planning stage. By the end of this year, we expect to know if the new poles can go in the existing locations and to have a construction schedule. Work will likely begin in late 2027 and should take less than a year.